MBInet.org      
  TODAY IS: Thursday, August 21, 2008
SEARCH:
MBInet.org
Modular Construction
 
Members Only Login
Username:
Password:
 
MBI members receive discounts, leads, free publications, and much more.
MBI MEMBERSHIP INFO

FREE MBI eNews

ABOUT MBI

CONTACT MBI

BOARD OF DIRECTORS

Rick McClymont 

"How to Document a Construction Claim"
The President's Message

October 2003
by Rick McClymont


As a manufacturer/direct, Britco Structures has over the years been involved in some major building projects. The usual format was for Britco to serve as a sub-contractor to a larger general contractor, although there have been occasions where we contracted directly with end-users of modular buildings. Thankfully, most of our projects have gone smoothly with very few problems. However, if a potential claim rears its head, manufacturers, dealers, and their customers would benefit greatly by following the basics outlined in the following article by Grant Mayovsky and Douglas Sanders.

* * *

At the outset of any construction project, when goodwill and trust are usually at their high points, the parties will often neglect to record in writing many of the key agreements and understandings reached between them. Later on in the project, when problems start to arise, trust and goodwill often give way to the financial realities of potential construction claims. More often than not, it is not until this latter point in time that the parties will start to thoroughly record events, as well as any agreements and understandings that may have been reached.

Failure to properly record and document construction projects can be fatal in a claim. Written agreements and documentary evidence will almost always outweigh oral evidence and alleged verbal agreements.

It is crucial to keep in mind the following items during the course of a project, which will help to support or defend a claim should one arise:

  1. Keep all bid documentation and record any pre-contractual agreements, representations and understandings in writing and ensure they are in the contract or can be relied upon at a later stage.
     
  2. Ensure that a fully signed written agreement is in place before commencing work on a project. While oral agreements are generally enforceable, written ones are easier to prove.
     
  3. Read and be familiar with all contract terms, especially the notice provisions. Failure to provide notification of a potential claim could preclude a party from bringing its claim.
     
  4. Keep all project correspondence. It is often helpful to organize project correspondence according to each key party and whether the correspondence is incoming or outgoing. For example, it is important to remember that in order to litigate a delay claim, it is generally necessary to reconstruct the project in detail on a daily basis.
     
  5. Record all relevant conversations and send follow up correspondence. Parties may proceed on a project for months based on a particular representation or understanding, only to find out later during litigation that the other party denies everything. Where there is no response to correspondence, a court may find that a failure to respond affirms what was said in the letter.
     
  6. Take pictures or videos at all stages of the project. Nothing can help a judge or lawyer more to understand a problem or deficiency on a project than an illustrative picture of it.
     
  7. Keep all plans and drawings and ensure that you have accurate records of all amendments or addendums.
     
  8. Make sure a project diary is kept along with diaries for key personnel. Diaries should record: 1) the weather; 2) manpower, visitors and contractors on site; 3) key deliveries; and 4) any notable event such as problematic or hidden site conditions or events that may cause delay or affect productivity. Ensure that entries express facts, rather than opinions.
     
  9. Maintain an as-planned schedule and regularly update it with an as-built schedule. There are several computer programs available to schedule and track progress. The end product of a proper scheduling exercise is a plan that should tell a contactor or owner what sequence work should be done in, when it should start, what work has to be completed first, when successor activities should start, and when it should finish. Having an accurate schedule for a project and regularly updating it will provide a valuable tool for tracking and recording delay and the impact of that delay.
     
  10. Record all key events, especially ones that may lead to a claim, and specifically record: 1) when the event occurred; 2) what it was; 3) who noticed it; 4) the projected impact it may have on cost and time; 5) whether notice was given and to whom; and 6) response to notice.
     
  11. Record all change orders and claims for extras and when they were submitted for approval, and separate those that are approved from those that are not. A contractor who has failed to get approval for a change order should always diligently express and protest their ongoing concerns writing. When doing so, the contractor should adhere to the contractual notice requirements. Parties should also be aware of the ability to give notice that they are performing under protest.
     
  12. Document the additional costs caused by an event. It is particularly important to keep proper accounting and employee payroll records pertaining to additional overhead and employee costs. Accounting records should be able to recreate the costs associated with particular tasks and problems as well as to create a snap shot of costs incurred at a particular point in a project.
     
  13. Finally, contact legal counsel as early as possible. Contractual interpretation and strategic decisions made early can greatly enhance your prospects for success in a construction claim.

Copyright © 2008 Modular Building Institute. All Rights Reserved.
Modular Building Institute | 944 Glenwood Station Ln., Ste. 204 | Charlottesville, VA 22901-1480 USA
Phone: 434-296-3288 | Toll Free: 888-811-3288
Fax: 434-296-3361 | Email: info@modular.org

PRINT PAGE:
Powered by Growing Technologies